Water Treatment and Storage Facility (WTF) Project
The City of Prior Lake Water Treatment Facility (WTF) project is underway and scheduled for completion in January 2009. Once operational, the facility will benefit the whole city.

Project Update
 
In addition to the precast being placed the past couple of weeks, the contractor is working on finishing the concrete walls in the filter/ detention tank area and stripping the shoring from the deck of the backwash holding tank. The plumber has been installing below grade piping for waste lines and installing roof drain piping in the filter building. The electrical subcontractor has been installing conduit below grade for the entire building.
Top left: The precast double tees is being set for the roof of the high service pump room above the clear well / reservoir.
Top right: The view from the south of the filter building with the footings for the garage and admin area in the foreground. Most of the building will be hidden by the garage when completed.
Bottom: The precast plank is being set for the aeration gallery floor.
Stay Informed
City will send regular emails notifying residents of the construction status and upcoming heavy-traffic activity. To be added to the email recipient list, go here and check the "Water Treatment Facility Updates" box.
|
Project information can be found in the City's Document Center, under current projects.
The Prior Lake City Council awarded the construction contract to Rice Lake Construction Group of Deerwood, Minn. on Aug. 6, 2007. Rice Lake was the low bidder on the project at $12,746,500.
Construction began in August 2007 with trucks driving to and from the site using Franklin Tr., Summer St., and Itasca Ave. Workers will remove excavated material then deliver concrete for the foundation. Later, there will be only limited traffic entering and leaving the site. Typical work hours will be Monday - Friday 7 a.m. - 5 p.m. RIce Lake's project superintendent is Thomas Leonard (612) 889-0799.
 
Above are
proposed perspectives
of the Water Treatment Facility.
Below is an aerial photo of the Water Treatment Facility Site location.
Click photo to enlarge

For more information, contact the Prior Lake Public Works Department at (952) 447-9830, Public Works Coordinator Jennifer Wittkopf at (952) 447-9833 or email here.
The project's consultant, Bolton & Menk, Inc., is at (952) 890-0509, or www.bolton-menk.com.
The project manager is Seth Peterson (612) 803-5223. The construction observer is Kelly Yahnke (612) 670-0140.
|